Project: Construction of a gypsum dewatering plant for blocks 1-6

Client: TPP Maritsa East 2, Bulgaria

Period of implementation: from 05.08.2009 to 29.09.2012,

Activities:

  • Design
  • Supply of basic and technological equipment:
    • Vacuum filters
    • Hydrocyclones
    • Band conveyors
  • Electrical equipment for transformer substations
  • CIP and A
  • Waste water tank
  • Gypsum storage facility
  • Installation of external and internal sewerage system
  • HVAC

„As a subcontractor,”Esco Engineering” JSC participates in the elaboration of the work projects by parts: “Machine Technology” and “HVAC”, the delivery of part of the facilities and author’s supervision.