Project: Consultancy services for the implementation of electrical installation related to the equipment of “Control and management system” and “Electric control” through PGR 2008 and PGR 2009 at 5 and 6 EB
Client: “Kozloduy NPP” EAD, Kozloduy
Implementation period: from 01.02.2008 to 31.10.2009
Activities:
- Preparation of design solutions for modernizing elements of SCC
- Preparing estimates of prepared technology maps
- Development of installation documentation – CMD drawings
- Supply of technological equipment, including:
- Execution fittings
- Regulating fittings
- Elements and materials for pulse lines
- Instruments by Part: I&C for Electric control Integration
- Assessment of the compliance of the equipment delivered by the main contractor with the requirements of the project